More than 20,000 segments produced for Metro Line 3 in Panama
The segments are being used for the approximately 4.5 kilometer long metro tunnel beneath the Panama Canal, which is excavated by the Herrenknecht TBM named Panama. The tunnel forms a central component of Metro Line 3, a major infrastructure project that will improve connectivity between Panama City's western suburbs and the city center.
For the first time in history, a tunnel boring machine is constructing a tunnel beneath the Panama Canal, one of the world's busiest waterways. The challenging geological conditions and strict project requirements called for sophisticated engineering solutions throughout the project. During excavation, the machine passes through varying geological conditions and reaches depths of more than 60 meters below sea level.
Herrenknecht Formwork supplied a comprehensive segment production package, including segment moulds for carousel production, handling equipment, measuring systems, curing technology and digital traceability solutions. Together, these technologies enabled the efficient, reliable and high-precision production of all tunnel lining segments required for the project.
The completion of segment production marks another major milestone on the way to the final breakthrough of the tunnel. The reliable supply of high-quality segments has played an essential role in supporting continuous TBM advance throughout the project.
A milestone achieved through teamwork
A key factor behind this success was the close cooperation between all project partners. In addition to Herrenknecht Formwork, several companies within the Herrenknecht Group contributed their expertise to the project, providing solutions for ground treatment, logistics and navigation.
The successful completion of 20,563 segments was the result of close cooperation, technical expertise and the commitment of all teams involved. Herrenknecht Formwork would like to thank the customer, partners and colleagues throughout the Herrenknecht Group for the excellent cooperation and their contribution to this important milestone.
We are grateful to have contributed to this project and look forward to the completion of Metro Line 3.